01/06/2009
Y&BC
Resurface pool
Add Verizon antenna to existing building
MK
Install emergency generators in Tommorowland
Install ice machine head at Pecos Bill's
Install conduit in utilidoors
Install new AEDs at multiple attractions
Replace roof on north rectifier building
GF
Resurface pool
CBR
Resurface Martinique pool
WL
Modify mechanical access doors in lobby
FT Wilderness
Construct expansion of 600 loop
DTD
Add Verizon antenna to Cirque building
CS
Add Verizon antenna to existing building
Epcot
Refurb Comucore fountain
Refurb column bases at gate in China
Refurbish pagoda building in Japan
Repair existing flat roofs in Japan
PORS
Replace dumpster pad
POFQ
Replace dumpster pad
AK
replace skylight in holding pen
Add fencing, gates and sunshade at holding pen
Install new AED's at several attractions
01/07/2009
MK
New stage in Tommorowland
New electrical panel
Provide conduit and wire for new IDS at Splash Mountain
Replace decking at Splash Mountain
New deck at Philarmagic
Epcot
Refurb kitchen of Electric Umbrella
Showset package for T Rowe Price exhibit
Boardwalk
Provide new electrical panel
CS
Reroute hood circuitry
Y&BC
Disconect hood circuitry
Contemporary
Disconnect hood circuitry in merchandise area
Remove section of railing and install new concrete at pool
AKL
Disconnect hood circuitry in Boma
TL
New kiddie slide
DHS
Replace chandlers in Sunset shops
Replace hot water tank at Sci-Fi
Replace piping at Catastrophe canyon
01/08/2009
Ft Wilderness
Set up 18 modular trailers (assuming new cabins for expansion)
North Service Area
New chiller and generator
Epcot
Refurb west restroom next to SSE
New AEDs at multiple attractions
Village lake
Replace sheet piles
MK
Replace carpet in Philarmagic
Y&BC
Resurface pool
Add Verizon antenna to existing building
MK
Install emergency generators in Tommorowland
Install ice machine head at Pecos Bill's
Install conduit in utilidoors
Install new AEDs at multiple attractions
Replace roof on north rectifier building
GF
Resurface pool
CBR
Resurface Martinique pool
WL
Modify mechanical access doors in lobby
FT Wilderness
Construct expansion of 600 loop
DTD
Add Verizon antenna to Cirque building
CS
Add Verizon antenna to existing building
Epcot
Refurb Comucore fountain
Refurb column bases at gate in China
Refurbish pagoda building in Japan
Repair existing flat roofs in Japan
PORS
Replace dumpster pad
POFQ
Replace dumpster pad
AK
replace skylight in holding pen
Add fencing, gates and sunshade at holding pen
Install new AED's at several attractions
01/07/2009
MK
New stage in Tommorowland
New electrical panel
Provide conduit and wire for new IDS at Splash Mountain
Replace decking at Splash Mountain
New deck at Philarmagic
Epcot
Refurb kitchen of Electric Umbrella
Showset package for T Rowe Price exhibit
Boardwalk
Provide new electrical panel
CS
Reroute hood circuitry
Y&BC
Disconect hood circuitry
Contemporary
Disconnect hood circuitry in merchandise area
Remove section of railing and install new concrete at pool
AKL
Disconnect hood circuitry in Boma
TL
New kiddie slide
DHS
Replace chandlers in Sunset shops
Replace hot water tank at Sci-Fi
Replace piping at Catastrophe canyon
01/08/2009
Ft Wilderness
Set up 18 modular trailers (assuming new cabins for expansion)
North Service Area
New chiller and generator
Epcot
Refurb west restroom next to SSE
New AEDs at multiple attractions
Village lake
Replace sheet piles
MK
Replace carpet in Philarmagic