They have an elevator at the Tiki Room? Don't recall seeing it, interesting. Also, some of the permits were tying down various sheds and merchandise carts. Was that preperation for hurricanes and such?
Not necessarily hurricanes, quite honestly WDW has to worry about severe thunderstorms which bring micro bursts and tornadoes more than hurricanes. It is common practice as well required by building code to tie these temporary structures down. I am pretty sure the lift is for the large anamatronic figure in center of the room.
 

Master Yoda

Pro Star Wars geek.
Premium Member
Original Poster
10/07/2008

MK

Replace 3 drinking fountains at PotC
Replace the dome at Cosmic Ray's

Admin Area

Remove sewer and electrical from trailers

PORS

Replace 2 chilled water handlers at commercial building

Vista Way

Repair leaking roof
Repair leaking roof

AK

Repalce existing kitchen at Petrifries
Times up sign fabrication and installation for Primeval Whirl

10/08/2008

DHS

Relocation of electrical and cabling in existing and new animation building

10/09/2008

North Service Area

Install 3 ton chiller

Epcot

Clean and paint steel under rockwork in Canada

DHS

Delete handrails at LMA to improve wheelchair access
Repair gray walls at Pixar place

Admin Area

Demolish Trailers

MK

Install (3) 25' poles with 1000w spot lights backstage behind old 20k site
Replace 14 existing dock panels backstage behind old 20k site

10/14/2008

Vista Way

Replace tile roofing with shingles

North service area

Rework header over door at monorail building

10/15/2008

DHS

Maintenance bay lighting at TSM

DTD

Hanes design a T sign

10/16/2008

Boardwalk

Replace tiles at entry

GF

Upgrade 3 elevators
Install new hot water isolation valves in building 6 and 7

Poly

Install new sand filter and chemical injection system for pond at great ceremonial house

TL

Replace wave pool

CS

Reline hot water pipes at Cabana 9B

MK

Install new bridge railings at Tomorrow land speedway overpass

10/17/2008

MK

Main Street cabinet installation with shroud and footer
Replace curtain controller, animation breakout boxes and automatic door controller

Epcot

Remove existing wall and replace with metal stud wall at WoL Pavilion

DHS

Narnia meet and greet addition
 

mcjaco

Well-Known Member
^ I may not be understanding your question correctly, but there always were two tracks/rides. A and B.

It's really just two wild mouse coasters set side by side. They bought two because they aren't good capacity eaters.
 

jhastings74

Well-Known Member
^ I may not be understanding your question correctly, but there always were two tracks/rides. A and B.

It's really just two wild mouse coasters set side by side. They bought two because they aren't good capacity eaters.

You understood it just fine. I was the one who was WAY confused....sorry!!! :brick:You were right. I meant to ask if there would still be two tracks, because there was talk of it being converted to just one track since it was such a quick ride...

Thanks for the virtual whack to the back of my head...! :)
 

Master Yoda

Pro Star Wars geek.
Premium Member
Original Poster
10/27/2008

Balnk. Contractor is a heating and air contractor.

BB

Duct work at tube and towel rental.

Epcot

Liberty Mutual electrical package

MK

HoP refurb control package

10/28/2008

Epcot

Rewire lighting truss at Innoventions West

10/29/2008

DHS

Install 120v outlets on light poles for Christmas lights at Pixar place.

Epcot

Pour concrete footer. Fabricate wood shroud and all electrical at UK pavilion
Pour concrete footer. Fabricate wood shroud and all electrical at Future world
T Rowe Price improvements/ demo package at Innoventions West.

AK

Install stand alone cabinet at conversation station
Install stand alone cabinet at Pangani trail
Modify existing hot wire boxes with new configuration
Modify existing hot wire boxes with new configuration

DTD

Install 4 weather proof outlets at Cirque
Install 2 decorative signs

TL

Rockwork at Mayday falls

MK

Install temporary construction bridge at Tomorrowland bridge
Paint handrails at front of MK
Replace stairs to second level of TL skyway building

North Service area

Install carpet at DU
Install carpet at DU
Install protective netting for rail system at laundry facility

ASM

Replace pool heater

CBR

Resurface quiet pool add handrails and mount for ADA lift
Resurface quiet pool add handrails and mount for ADA lift

CS

Resurface quiet pool add handrails and mount for ADA lift

FW

Replace pool heater

PORS

Replace pool heater
Resurface quiet pool add handrails and mount for ADA lift
Resurface quiet pool add handrails and mount for ADA lift

10/30/2008

Epcot

Install wireless antenna for cell service in Germany pavilion
Install wireless antenna for cell service in Mexico pavilion
Install wireless antenna for cell service in Norway pavilion
Install wireless antenna for cell service in UK pavilion
Install wireless antenna for cell service in France pavilion
 

RiversideBunny

New Member
What is 'HoP' in the MK? (10/27)
I'm drawing a blank on that.
Tks.
:)

Edit: OH- wait, wait. I know. Hall of Presidents.

For some reason I was stuck on 'House of Pancakes'.
 

jedimaster1227

Active Member
Thanks for posting those, why would they be replacing the stairs at the old sky way building, maybe it gets used alot for storage still?

Considering our Timekeeper animatronic as well as several Skyway buckets are sitting up there, among other things, yes it is still used for storage.

But, the building itself is still capable of other uses...
 

Register on WDWMAGIC. This sidebar will go away, and you'll see fewer ads.

Back
Top Bottom