I figured that it would take a few weeks. I was guessing 3 weeks with 5 working days a week, but they are only doing 4 working days. So I would say 3.5 now to get the structure down. They can do the other things at a slower rate it they want as long as it's down.
It is 5 working days a week but you are correct in the timeframe. This is a 4 week job barring anything unforeseen happening.
The segmental steel structure should not take a long time to remove as it is relatively easy to cut and rig as opposed to the odd shaped and unbalanced letters/ribbon/wand.