peter11435
Well-Known Member
Really?
Yes. Some of the smaller dinosaurs were sent there. Likely to be used for replacement parts for the Primevil World Diorama.
Really?
That stinks. I was hoping we’d get our own diorama, however unlikely.Yes. Some of the smaller dinosaurs were sent there. Likely to be used for replacement parts for the Primevil World Diorama.
Why frowny? That ought to be cool.Walt Disney World Railroad will go under Tron ride just like in the Concept Art from D23 Expo last year?
Maybe during the day, we'll see more activity !Kinda dark but from the top of the contemporary. Still not much going on...View attachment 298066View attachment 298067
Maybe during the day, we'll see more activity !
Site prep is really the easy part. It’s being done now because it can so easily overlap with design work.Ground work is one of the longest and most boring parts of any job.... I just built a 10K square foot addition for loading docs and the ground work on this little project was the entire time line and it took 9 months to complete and it is just warehouse space... Sad but we dont know what all has to be done on these projects to get the pads ready for this.... Not making excuses but reality
Site prep is really the easy part. It’s being done now because it can so easily overlap with design work.
Yes, and all of that work is being done while design work continues on the rest of the building.If you say so... but to get a pad ready for construction and to pour the floor is a big job... It takes a long time and you dont see much progress until steel goes up... To me pad ready site ready is when all underground utility work is done and site is ready for foundation to be dug out framed and poured...
Ground work is one of the longest and most boring parts of any job.... I just built a 10K square foot addition for loading docs and the ground work on this little project was the entire time line and it took 9 months to complete and it is just warehouse space... Sad but we dont know what all has to be done on these projects to get the pads ready for this.... Not making excuses but reality
Site prep is really the easy part. It’s being done now because it can so easily overlap with design work.
If you say so... but to get a pad ready for construction and to pour the floor is a big job... It takes a long time and you dont see much progress until steel goes up... To me pad ready site ready is when all underground utility work is done and site is ready for foundation to be dug out framed and poured...
Yes, and all of that work is being done while design work continues on the rest of the building.
*ChinaYou're both incorrect. All they needed to do was fly a helicopter over to Japan and hit CTRL C and then fly to WDW and hover over the area near SM and hit CTRL V and....Boom!
Site prep easy, yes, but extremely time consuming!Site prep is really the easy part. It’s being done now because it can so easily overlap with design work.
Would have been cool if they could have extended the Peoplemover to also go through the Tron coaster building as well.
Eh, they're ain't any cranes to be had...
Do we actually know for a fact that when they were designing the new ride they did not also pre configure everything to be also built in the US? I mean, with the frequency of clone building, you would think they would have just had the Shanghai version be designed to fit compliance in all countires the ride could be used... I mean, it is not like they are starting from the ground up all over again with the design... Yes, site changes but most likely not everything....You're both incorrect. All they needed to do was fly a helicopter over to Japan and hit CTRL C and then fly to WDW and hover over the area near SM and hit CTRL V and....Boom! I mean it's a clone, right? Who needs core borings or civil work or structures re-engineered or ADA compliance upheld or.....anything that prevents fans from riding TRON!!!!
If only it were this easy.
Register on WDWMAGIC. This sidebar will go away, and you'll see fewer ads.