Another interesting difference in how this is being constructed from Anaheim can be seen in how the highest piece that castmembers were allowed to sign had its mesh-work installed before installation. Would have been neat if they went another step further and just installed a fully painted piece as they did with the peak of the Disneyland Thunder Mountain, and more recently with the highest floating mountain at Pandora.
 
Last edited:

sedati

Well-Known Member
Did some quick research and Disneyland had their topping off in late August. A little over three months ago. And yet, there was no mesh installed at all- not just on the highest peak, but the neighboring ones as well. Florida has a good deal of rockwork mesh already up.
 

HauntedMansionFLA

Well-Known Member
That sounds like someone repeating what Spirit said, namely, that when SWGEB opens in DHS it won't be fully finished and work will continue into 2020.

No other insider that I know of says the same.
Well, it will be interesting to see how things progress. I live close by and will be snapping pictures to compare progress. You have to take notice when Spirit makes a comment especially after he broke “What are we going to do with John” months ago :)
 

MisterPenguin

President of Animal Kingdom
Premium Member
Well, it will be interesting to see how things progress. I live close by and will be snapping pictures to compare progress. You have to take notice when Spirit makes a comment especially after he broke “What are we going to do with John” months ago :)

While Spirit definitely has inside info that is good, it's not always perfect. He was predicting DHS's SWL to be over a year behind DL's. And then recently prevaricated over sources when it wound up he would be obviously wrong and then he said it wouldn't be fully finished when it opened in late 2019.
 

HauntedMansionFLA

Well-Known Member
While Spirit definitely has inside info that is good, it's not always perfect. He was predicting DHS's SWL to be over a year behind DL's. And then recently prevaricated over sources when it wound up he would be obviously wrong and then he said it wouldn't be fully finished when it opened in late 2019.
I’ll keep myself updated on your rumor thread
 

BrianLo

Well-Known Member
Spirit is a bad Nostradamus on timelines, when he is guessing, which he was. There is no serious indication that WDW's land is majorly sliding and I have seen nothing to suggest DL's can't be operational in the first half of 2019, if not the first quarter.

Next time points I'm watching for is:
1. The topping out of MF's tallest peak. Due the final week of Nov/start of December if we're on that ~3.5 month pace still, versus slipped.
2. The three peaks over the show building roof should have received their full scaffolding around the third week of January.

Clearly MF is keeping pace, so I'll propose a few other areas to watch for in the coming months:

1. By the second week of March 90% of the front side of Battle Escape should have its rock work steel up.
2. The land's large building supporting the semi-covered market should have about 75% of its steel and the archway over the entrance to the market street.



Finally, SW:GE in DHS would have to look worse than this for me to be seriously concerned it was becoming difficult to open it in 2019.

x4nomh.jpg
 

Master Yoda

Pro Star Wars geek.
Premium Member
Spirit is a bad Nostradamus on timelines, when he is guessing, which he was. There is no serious indication that WDW's land is majorly sliding and I have seen nothing to suggest DL's can't be operational in the first half of 2019, if not the first quarter.



Clearly MF is keeping pace, so I'll propose a few other areas to watch for in the coming months:

1. By the second week of March 90% of the front side of Battle Escape should have its rock work steel up.
2. The land's large building supporting the semi-covered market should have about 75% of its steel and the archway over the entrance to the market street.



Finally, SW:GE in DHS would have to look worse than this for me to be seriously concerned it was becoming difficult to open it in 2019.

x4nomh.jpg
Most people that are not directly involved with a particular project and/or familiar with construction are. What looks like complete chaos and months worth of work to layman often looks quite different to someone that does this stuff day in and day out.
 