PERMITS

SSG

Well-Known Member
Original Poster
Hotel work

BLD2018-02760 Paradise Pier Hotel - Pool Slide Equipment Room, Tank/Piping - Tenant Improvement: Replace (3) existing 12,150 lbs water tanks anchored to existing slab.

BLD2018-02649 Disneyland Hotel - Frontier Tower - Tenant Improvement: Replacement of (4) Heat Exchangers serving the domestic hotel water and provide (2) new buffer tanks with a new pour-in-place pad, located in the basement.
 

SSG

Well-Known Member
Original Poster
Interesting:

BLD2018-02765 DTD - Adjacent DLAND Gate 33 - Pedestrian Routing Check Point - Tenant Improvement: 7400 s.ft canopy walk way. 300 ln.ft x 8' high metal fencing. (12) security tents (permit not required). Alteration to existing parking lot to accommodate new security check point.
 

SSG

Well-Known Member
Original Poster
There's your Falcon (maybe)

BLD2018-02794 Disneyland - SW - DL Frontierland Expansion - Area Site Development Adjacent to Bldg 1007 - New Steel Sculpture Ship Anchored to Existing Pad. Foundation under permit BLD2017-02850

And your Hideaway

BLD2018-02806 Status: Received Map Info: 1313 S HARBOR BLVD 2101 (Enchanted Tiki Room) Disney - Building 800 - Tenant Impovement: 1,300 sq ft canopy with (8) steel posts.

And hotel expansion

BLD2018-02789 DTD - Adjacent to Gate 28 - (2) Temporary Construction Trailers with Electrical and plumbing connections for future Hotel.
 

Disney Irish

Premium Member
There's your Falcon (maybe)

BLD2018-02794 Disneyland - SW - DL Frontierland Expansion - Area Site Development Adjacent to Bldg 1007 - New Steel Sculpture Ship Anchored to Existing Pad. Foundation under permit BLD2017-02850

And your Hideaway

BLD2018-02806 Status: Received Map Info: 1313 S HARBOR BLVD 2101 (Enchanted Tiki Room) Disney - Building 800 - Tenant Impovement: 1,300 sq ft canopy with (8) steel posts.

And hotel expansion

BLD2018-02789 DTD - Adjacent to Gate 28 - (2) Temporary Construction Trailers with Electrical and plumbing connections for future Hotel.

its-all-happening-gif-4.gif
 

SSG

Well-Known Member
Original Poster
BLD2018-02956 DTD - Building E / Suite 101 (DISNEY-DTD SALT & STRAW) Electrical to install (1) 45kba transformer, (2) 100amp subpanel, (1) 150amp subpanel and underfloor raceway with receptacles. REF: BLD2018-01749

BLD2018-02948 Disney - BOH - Westside Diner - Remove (3) existing hot water pumps from 2nd floor mechanical room, relocate hot water pumps to roof location.
 

SSG

Well-Known Member
Original Poster
Lots today:

BLD2018-02986 Electrical to reference Tenant Improvement permit BLD2018-00997 - Disney / Tomorrowland - Operation Office TI. (BLD2018-00997 is Disney - Tomorrowland / Operation Office TI - Non Residential Addition: Starcade floor (previously escalator/speed ramp) to be infilled to extend 2nd floor area 160 s.ft. Construct two exit openings to lead to new exit stairs. Tenant Improvement: 1,375 s.ft modifications to existing operations office to include new ceiling, drywall, and electrical, mechanical.)

BLD2018-02987 Electrical to reference Tenant Improvement permit BLD2018-01545 for Disney - Space Mountain, Backstage (BLD2018-01545 is Disney - Space Mountain, Backstage - Tenant Improvement: Renovate 5000 sq. ft. existing interior space to a conditioned queue area. Reconfigure exiting queue on roof deck. Associated electrical and finish modifications)

BLD2018-02992 Electrical to reference permit BLD2018-01860 located DCA - Guardian of the Galaxy - Mechanical units. (BLD2018-01860 is DCA - Guardian of the Galaxy - Tenant Improvement: Install (2) new ground mounted fan coils with ducting, and electrical. Install (2) condensate pumps.)

BLD2018-02991 Electrical to reference tenant Improvement permit BLD2018-02276 for GCH - Elevator Lobby Entrance. (BLD2018-02276 is GCH - Elevator Lobby Entrance - Tenant Improvement: Enlarge existing entry door.)

BLD2018-02995 Plumbing to reference BLD2018-01749 located at DTD - Building E / Suite 101 (DISNEY-DTD SALT & STRAW). (BLD2018-01749 is DTD - Building E / Suite 101 - Change of Use: 952 sq.ft. for new non-load bearing partition walls, new kitchen area, walking freezer and new guest area, mechanical, electrical, and plumbing throughout. Facade renovation new exterior lighting and (7) awnings, 100 sq.ft tile veener and modified door. "Salt and Straw".)

BLD2018-03008 DTD - Building D, Suite 104 - Tenant Improvement: Removal of non-bearing interior partition walls, fixtures and ceiling to return to core and shell for future tenant. (104 is Wetzel's Pretzel's )

BLD2018-02990 Electrical to reference Tenant Improvement permit BLD2018-02030 for DLH - Convention Center / Sleeping Beauty Pavilion

BLD2018-02989 Electrical; replace motor for catching vehicles located Disney - Matterhorn Bobsleds

SGN2018-00106 Installation of illuminated channel letters on canopy and wall reads " Splitsville".
 
Last edited:

Disney Irish

Premium Member
Lots today:

BLD2018-02986 Electrical to reference Tenant Improvement permit BLD2018-00997 - Disney / Tomorrowland - Operation Office TI. (BLD2018-00997 is Disney - Tomorrowland / Operation Office TI - Non Residential Addition: Starcade floor (previously escalator/speed ramp) to be infilled to extend 2nd floor area 160 s.ft. Construct two exit openings to lead to new exit stairs. Tenant Improvement: 1,375 s.ft modifications to existing operations office to include new ceiling, drywall, and electrical, mechanical.)

BLD2018-02987 Electrical to reference Tenant Improvement permit BLD2018-01545 for Disney - Space Mountain, Backstage (BLD2018-01545 is Disney - Space Mountain, Backstage - Tenant Improvement: Renovate 5000 sq. ft. existing interior space to a conditioned queue area. Reconfigure exiting queue on roof deck. Associated electrical and finish modifications)

BLD2018-02992 Electrical to reference permit BLD2018-01860 located DCA - Guardian of the Galaxy - Mechanical units. (BLD2018-01860 is DCA - Guardian of the Galaxy - Tenant Improvement: Install (2) new ground mounted fan coils with ducting, and electrical. Install (2) condensate pumps.)

BLD2018-02991 Electrical to reference tenant Improvement permit BLD2018-02276 for GCH - Elevator Lobby Entrance. (BLD2018-02276 is GCH - Elevator Lobby Entrance - Tenant Improvement: Enlarge existing entry door.)

BLD2018-02995 Plumbing to reference BLD2018-01749 located at DTD - Building E / Suite 101 (DISNEY-DTD SALT & STRAW). (BLD2018-01749 is DTD - Building E / Suite 101 - Change of Use: 952 sq.ft. for new non-load bearing partition walls, new kitchen area, walking freezer and new guest area, mechanical, electrical, and plumbing throughout. Facade renovation new exterior lighting and (7) awnings, 100 sq.ft tile veener and modified door. "Salt and Straw".)

BLD2018-03008 DTD - Building D, Suite 104 - Tenant Improvement: Removal of non-bearing interior partition walls, fixtures and ceiling to return to core and shell for future tenant. (104 is Wetzel's Pretzel's )

BLD2018-02990 Electrical to reference Tenant Improvement permit BLD2018-02030 for DLH - Convention Center / Sleeping Beauty Pavilion

BLD2018-02989 Electrical; replace motor for catching vehicles located Disney - Matterhorn Bobsleds

SGN2018-00106 Installation of illuminated channel letters on canopy and wall reads " Splitsville".

Hmm, some of these SM permits conflict with previous ones. So is the exit now going to be interior and the entrance still going to be exterior? Or are they both going to be interior?
 

Old Mouseketeer

Well-Known Member
Hmm, some of these SM permits conflict with previous ones. So is the exit now going to be interior and the entrance still going to be exterior? Or are they both going to be interior?

I asked one of my Rebel Spies to check on this. My Bothan reports that you can see the new stairs coming down from the back of the upper level of Starcade directly above the backstage exit from the handicapped entrance/general exit of Space Mountain (to the left of the men' room and drinking fountain). It's a double-wide staircase with a landing at mid-point and a handrail down the middle. Sadly this spy is retiring soon. Good Bothans are hard to come by.
 

Disney Irish

Premium Member
I asked one of my Rebel Spies to check on this. My Bothan reports that you can see the new stairs coming down from the back of the upper level of Starcade directly above the backstage exit from the handicapped entrance/general exit of Space Mountain (to the left of the men' room and drinking fountain). It's a double-wide staircase with a landing at mid-point and a handrail down the middle. Sadly this spy is retiring soon. Good Bothans are hard to come by.

That still doesn’t answer any of the questions I asked....
 

180º

Well-Known Member
I asked one of my Rebel Spies to check on this. My Bothan reports that you can see the new stairs coming down from the back of the upper level of Starcade directly above the backstage exit from the handicapped entrance/general exit of Space Mountain (to the left of the men' room and drinking fountain). It's a double-wide staircase with a landing at mid-point and a handrail down the middle. Sadly this spy is retiring soon. Good Bothans are hard to come by.
Nice to hear this project’s coming along. Sad to lose the speed ramp forever, but it wasn’t doing anyone any good sitting unused.
That still doesn’t answer any of the questions I asked....
I think I may have figured out your question. Think of “exit stairs” in terms of emergency exit stairs for the new queue, not stairs that service the attraction exit. I’m fairly certain everything else about the project is the same since we last discussed it. :)
 

Disney Irish

Premium Member
Nice to hear this project’s coming along. Sad to lose the speed ramp forever, but it wasn’t doing anyone any good sitting unused.

I think I may have figured out your question. Think of “exit stairs” in terms of emergency exit stairs for the new queue, not stairs that service the attraction exit. I’m fairly certain everything else about the project is the same since we last discussed it. :)

Maybe, but they mention "Construct two exit openings to lead to new exit stairs." in the permit not emergency exit stairs. So that still doesn't line up.

But hey I guess in a couple months we'll all find out.
 

SSG

Well-Known Member
Original Poster
Maybe, but they mention "Construct two exit openings to lead to new exit stairs." in the permit not emergency exit stairs. So that still doesn't line up.

But hey I guess in a couple months we'll all find out.
Keep in mind that the permit requires just a brief description of the project, there are often multiple permits associated one project, and often different people apply for permits, even when it's for the same project. Not too surprising that things get lost in translation.
 

SSG

Well-Known Member
Original Poster
Maybe, but they mention "Construct two exit openings to lead to new exit stairs." in the permit not emergency exit stairs. So that still doesn't line up.

But hey I guess in a couple months we'll all find out.
This just in:

BLD2018-03029 Disney - Space Mountain/Balloon Room - Tenant Improvement: Modifications to queue stair egress to include new walls, stairs, landing, ceiling and retaining walls.
 

TP2000

Well-Known Member
Veranda?

SGN2018-00107 Status: Issued Map Info: 1313 S DISNEYLAND DR (Mickey and Friends Parking Structure) Installation of illuminated blade sing that reads "THE VERANDA"

I will try very hard here to not start another unfounded rumor about a cocktail lounge, like my Treetop Tapas N' Tipples idea when a similar permit came in for Adventureland and it only turned out to be more stroller parking. :(

But... they are going to label a new part of this massive parking structure The Veranda? They would need that for placemaking and wayfinding purposes, obviously. But why call out an area of a 16,500 space parking facility as The Veranda? Perhaps this is what they will be calling the expanded and reconfigured tram loading zone?
 

Disney Irish

Premium Member
Veranda?

SGN2018-00107 Status: Issued Map Info: 1313 S DISNEYLAND DR (Mickey and Friends Parking Structure) Installation of illuminated blade sing that reads "THE VERANDA"

I will try very hard here to not start another unfounded rumor about a cocktail lounge, like my Treetop Tapas N' Tipples idea when a similar permit came in for Adventureland and it only turned out to be more stroller parking. :(

But... they are going to label a new part of this massive parking structure The Veranda? They would need that for placemaking and wayfinding purposes, obviously. But why call out an area of a 16,500 space parking facility as The Veranda? Perhaps this is what they will be calling the expanded and reconfigured tram loading zone?

I have a feeling its just a wayfinder sign to the Veranda in GCH:

https://disneyparks.disney.go.com/b...lifornian-hotel-spa-at-the-disneyland-resort/
 
Last edited:

SSG

Well-Known Member
Original Poster
I will try very hard here to not start another unfounded rumor about a cocktail lounge, like my Treetop Tapas N' Tipples idea when a similar permit came in for Adventureland and it only turned out to be more stroller parking. :(

But... they are going to label a new part of this massive parking structure The Veranda? They would need that for placemaking and wayfinding purposes, obviously. But why call out an area of a 16,500 space parking facility as The Veranda? Perhaps this is what they will be calling the expanded and reconfigured tram loading zone?
Just a guess, but a plaza area selling refreshments perhaps? Maybe some shade and seating. If you're giving an area a name, you'd think something would be there other than open space.
 