2 months shy of 3 years from announcement to Grand Opening for a flat and a Jr. coaster.
Good to see TDO is aggressively addressing the capacity issues of this sad little park.
Going by announcement isn't a fair way to judge construction.
Going from groundbreaking, TSL will be 27 months (2.2 years). Three months shy of each of the Potter Lands, which isn't saying they were speedy since the scope of TSL is much less. But, let's not throw around "almost 3 years" when it's really "a little more than two years."