Buzz2001 Well-Known Member Apr 6, 2009 #1 The rehab at CSR is now moving to casita 4. All the cabana buildings are complete as are ranchos 6a and 6b. The 4th floors in casita 1, 2 and 3 are done as well. All looks on schedule to be complete by 10/2009.
The rehab at CSR is now moving to casita 4. All the cabana buildings are complete as are ranchos 6a and 6b. The 4th floors in casita 1, 2 and 3 are done as well. All looks on schedule to be complete by 10/2009.
Buzz2001 Well-Known Member Original Poster Aug 25, 2009 #61 La Marina reopened two weeks early, on Monday, August 24th. Upvote 0
Buzz2001 Well-Known Member Original Poster Sep 12, 2009 #62 All room renovations are complete and life is back to normal at CSR!! Upvote 0