News Disneyland Resort Permits

SSG

Well-Known Member
Original Poster
01/23/2025
BLD2025-00348
Building Permit
1351 S DISNEYLAND DR, Anaheim CA 92802
Issued
Electrical to support DLR - West of West Parking Lot - Resort Overall - Tenant Improvement.
01/24/2026


1313 S HARBOR BLVD
MORROW - MEADOWS CORPORATION
Project Description:
Electrical to support DLR - Jolly Holiday/BLDG #1002 - Tenant Improvement. REF:BLD2024-04275


01/23/2025
BLD2025-00357
Building Permit
1600 S DISNEYLAND DR, ANAHEIM CA 92802
Plan Review
DLR - CONF
01/23/2026
 

SSG

Well-Known Member
Original Poster

BLD2025-00413
Building Permit
1515 S HARBOR BLVD, 753, ANAHEIM CA 92802[/td]
Ready to Issue
Plumbing to support DCA - PYM Test Kitchen/BLDG #753 - Tenant Improvement. REF BLD2024-01695

BLD2025-00412
Building Permit
1313 S HARBOR BLVD, 7810, Anaheim CA 92802[/td]
Ready to Issue
Electrical to support DLR - It's A Small World/BLDG #7810 - Tenant Improvement. REF BLD2024-05846


777 W KATELLA AVE 421 92802
Project Description:
DCA - Golden Vine House - Tenant Improvement: replace (3) exterior light fixtures with new wall anchorage. With electrical.
 

SSG

Well-Known Member
Original Poster
01/30/2025
BLD2025-00051-REV01
Plan Revision
333 W DISNEY WAY, ANAHEIM CA 92802
Plan Review
DLR - Pumba Lot - Disneyland Half Marathon - Miscellaneous: Install (2) directional towers and (1) truss arch. Electrical for (4) temp generators. (01-24-25 thru 02-02-25)
01/30/2025

BLD2022-05697-REV09
Plan Revision
1717 S DISNEYLAND DR, ANAHEIM CA 92802
Plan Review
PPH - Main Tower - Tenant Improvement: Upgrades to corridors and (481) guestrooms on floors 3-15. Replace exterior windows and sliding doors/sidelite/transom systems in guest rooms and corridors. Replace elevator lobby swing doors with slilding won-door system. With mechanical, electrical and plumbing.

01/30/2025
BLD2025-00485
Building Permit
1553 S DISNEYLAND DR, ANAHEIM CA 92802
Ready to Issue
DTD - QSR #2 - Electrical: 100 amp subpanel to support construction trailer and spider box.
01/30/2026

01/29/2025
BLD2025-00464
Building Permit
1545 S DISNEYLAND DR, Anaheim CA 92802
Ready to Issue
Mechanical and Plumbing to support DTD - Building CC - Change of Use. REF:BLD2024-05156
01/29/2026

01/30/2025
BLD2025-00476
Building Permit
1313 S HARBOR BLVD, 2303, ANAHEIM CA 92802
Plan Review
DLR - Jungle Cruice/BLDG #2303 - Tenant Improvement: Remove and replace (2) freestanding structures that include footings, steel frame and rockwork. With electrical.
01/30/2026

01/29/2025
BLD2025-00469
Building Permit
1313 S HARBOR BLVD, 4400, Anaheim CA 92802
Issued
Electrical to support DLR - BOH - Winnie the Pooh/BLDG 4400 - Tenant Improvement. REF:BLD2023-04217
01/31/2026

01/29/2025
BLD2025-00467
Building Permit
1313 S HARBOR BLVD, 8900, Anaheim CA 92802
Issued
Electrical to support DLR - BOH - Finding Nemo/BLDG 8900 - Tenant Improvement. REF:BLD2023-04216
01/31/2026

01/29/2025
BLD2025-00444
Building Permit
1313 S HARBOR BLVD, 7600, ANAHEIM CA 92802
Plan Review
DLR - Matterhorn Bobsleds/BLDG #7600 - Tenant Improvement: Replacement of and installation of new cameras and illuminators. Modify existing rockwork and install new. Install new fall protection. With electrical.
01/29/2026
 

SSG

Well-Known Member
Original Poster


SGN2025-00014745 W Katella Ave Anaheim, Ca 92802
2/3/2025Third Floor North Company
(714) 556 0990
08228043
$0.00Dca - Cars Land - Installation Of (2) Non-illuminated Signs "red's Garden".



02/04/2025

BLD2024-01695-REV01

Plan Revision

1515 S HARBOR BLVD, 753, ANAHEIM CA 92802

Plan Review

DCA - PYM Test Kitchen/BLDG #753 - Tenant Improvement: Install (1) new exterior walk-in cooler on new concrete pad. With electrical and plumbing.

02/04/2025

BLD2024-05846-REV01

Plan Revision

1313 S HARBOR BLVD, 7810, Anaheim CA 92802

Plan Review

DLR - It's A Small World/BLDG #7810 - Tenant Improvement: Construct walls to create (5) powered electronic room closets with dimmer racks. Mechanical to condition the rooms. Electrical to change out lights to LED fixtures with structural supports.

02/04/2025

BLD2025-00546

Building Permit

1313 S HARBOR BLVD, 2101, ANAHEIM CA 92802

Plan Review

DLR - Tiki Room/BLDG #2101 - Tenant Improvement: Replacement of exterior show prop with isolated footing. Electrical to replace show lighting, audio systems and door actuators.
 

SSG

Well-Known Member
Original Poster
02/05/2025, BLD2025-00577
Building Permit, 1313 S HARBOR BLVD, 2501, ANAHEIM CA 92802
Plan Review
DLR - Indiana Jones - Tenant Improvement: Replace animation hydraulic power unit anchored on to existing pad and replace emergency eyewash station. With electrical, mechanical and plumbing.
 

Misted Compass

Well-Known Member
02/05/2025, BLD2025-00577
Building Permit, 1313 S HARBOR BLVD, 2501, ANAHEIM CA 92802
Plan Review
DLR - Indiana Jones - Tenant Improvement: Replace animation hydraulic power unit anchored on to existing pad and replace emergency eyewash station. With electrical, mechanical and plumbing.
Looks like the upcoming refurb is related to both this and the "moving room" permit.
 

TheDisneyParksfanC8

Well-Known Member
DCA - Hyperion Theater/BLDG #304 - Electrical to install (3) cart charger stanchions.
01/13/2026
What could these be for? I was under the motion that Disney had no plans to put another theater production in the Hyperion and the building would be leveled for either Avatar or Avengers Campus expansion.
 

NobodyElse

Well-Known Member
What could these be for? I was under the motion that Disney had no plans to put another theater production in the Hyperion and the building would be leveled for either Avatar or Avengers Campus expansion.
It could just be electrical to install (3) cart charger stanchions on or near the exterior of that building, to charge the carts they use for tooling around back-stage, having little or nothing to do with theatrical production.
 

SSG

Well-Known Member
Original Poster
1150 W MAGIC WAY 92802

DLH - Adventure Tower - Change of Use: 1,550 sq ft of existing (R1) to be converted to (B) and (A2) with 750 sq ft of existing (A2) and 1,200 sq ft of existing (B) to be remodeled for expansion of concierge lounge. Improvements to include restrooms, enlarged buffet, beverage counter and seating. With mechanical, electrical and plumbing.

1717 S DISNEYLAND DR 92802

PPH - Electrical to replace (27) subpanels, disconnects and transformers throughout the hotel.
 

disneylandcm

Well-Known Member
1150 W MAGIC WAY 92802

DLH - Adventure Tower - Change of Use: 1,550 sq ft of existing (R1) to be converted to (B) and (A2) with 750 sq ft of existing (A2) and 1,200 sq ft of existing (B) to be remodeled for expansion of concierge lounge. Improvements to include restrooms, enlarged buffet, beverage counter and seating. With mechanical, electrical and plumbing.

1717 S DISNEYLAND DR 92802

PPH - Electrical to replace (27) subpanels, disconnects and transformers throughout the hotel.
I have always believed that (R1) would be better served as additional (B) IF combined with (A2)! However, (A2) as it is today needs a redesign as it was…. I HAVE NO IDEA WHAT I’M TALKING ABOUT!
 

TheCoasterNerd

Well-Known Member
1616 S Disneyland Dr 503 Anaheim, Ca 92802 BLD2025-00687: Dca - Incredicoaster/Bldg #503 - Tenant Improvement: Infill (4) Skylights To Match Current Metal Roofing. Install (8) Fans. With Electrical.
Oh man... if those are the skylights in the queue, that sucks. Those are awesome visually. But it does make sense for summer cause it gets hot in that queue
 

Dapale

Well-Known Member
01/17/2025
BLD2025-00279
Building Permit
1313 S HARBOR BLVD, 2501, ANAHEIM CA 92802
Plan Review
DLR - Indiana Jones - Tenant Improvement: Replace control system for moving room with new guardrails and associated electrical.
01/17/2026
02/05/2025, BLD2025-00577
Building Permit, 1313 S HARBOR BLVD, 2501, ANAHEIM CA 92802
Plan Review
DLR - Indiana Jones - Tenant Improvement: Replace animation hydraulic power unit anchored on to existing pad and replace emergency eyewash station. With electrical, mechanical and plumbing.
1313 S HARBOR BLVD DLR - BLD2024-05631-REV01 Plan Revision- Indiana Jones Adventure/BLDG #2501 - Tenant Improvement: Plumbing and electrical to install new fog/mist system with new piping, fans and nozzles

Crazy theory guys... Hear me out

Permit 1: General maintenance & back-of-house work on boulder scene (as many have said already)
Permit 2 & 3: Finally finishing the vision of the "Gates of Doom" scene:
- Permit 2 = fixing the gate door (allowing Indy to close it again)
- Permit 3 = installing the intended fog & mist that's supposed to appear below and on the track.

The original intention of that scene is that you're "floating towards the gates of doom" then Indy shuts the door and you fall onto the ground, now able to drive. Indy shutting the door USED to work, but hasn't for awhile. I'm not sure if there was ever mist/fog in the beginning that was intended. I don't see why "new fog & mist" would apply to the temple room/lava pit because that HAS been working. I feel like the wording would've been "replace" if it was for that scene.

The moment I saw the second permit it screamed out animatronic/motion work. Then the third permit came in... I could totally be wrong but this is what I'm hoping it is.
 

Misted Compass

Well-Known Member
Crazy theory guys... Hear me out

Permit 1: General maintenance & back-of-house work on boulder scene (as many have said already)
Permit 2 & 3: Finally finishing the vision of the "Gates of Doom" scene:
- Permit 2 = fixing the gate door (allowing Indy to close it again)
- Permit 3 = installing the intended fog & mist that's supposed to appear below and on the track.

The original intention of that scene is that you're "floating towards the gates of doom" then Indy shuts the door and you fall onto the ground, now able to drive. Indy shutting the door USED to work, but hasn't for awhile. I'm not sure if there was ever mist/fog in the beginning that was intended. I don't see why "new fog & mist" would apply to the temple room/lava pit because that HAS been working. I feel like the wording would've been "replace" if it was for that scene.

The moment I saw the second permit it screamed out animatronic/motion work. Then the third permit came in... I could totally be wrong but this is what I'm hoping it is.
Did Indy actually physically close the door? Everything I've read has said the effect was just turning off the light behind to make it appear that the door was shut.

Regardless, the fog permit makes it clear that some major work is going to be done in the upcoming refurb.
 

Dapale

Well-Known Member
Everything I've read has said the effect was just turning off the light behind to make it appear that the door was shut.
Honestly this might be true, I couldn't verify it. Nonetheless, I think my theory could still apply because they physically altered the Indy figure's position & location at some point (not sure when) since the door closing effect doesn't occur anymore. So the permit still may be related to relocating the figure or something?
 