Any information on POFQ? They were renovating Building 4 when Iwas down for the marathon. According to a display in the food court, they were changing the interiors, taking out the pedestal sinks, changing the color scheme, etc.
Disney’s Port Orleans Resort – French Quarter
Now – Feb. 11, 2011: Building 5 roof recovering.
Feb. 6 – March 4, 2011: Building 1 roof recovering.
Feb. 13 – March 8, 2011: Bridge Stonework refinishing and repainting.
Feb. 27 – March 25, 2011: Building 2 roof recovering.
Mar. 20 – April 15, 2011: Building 3 roof recovering.