The road projects include:
A flyover will take resort traffic over the Magic Kingdom's toll plaza, providing easier access to travelers heading to hotels such as the Contemporary and Polynesian Village resorts, said John Classe, a Reedy Creek deputy administrator. Right now hotel visitors must drive through the parking plaza, even though they don't have to pay.
•A reconfiguration of Osceola Parkway at Victory Way, southeast of Disney's Hollywood Studios and north of ESPN Wide World of Sports Complex. A traditional intersection will be replaced with a flyover design similar to that at state roads 50 and 436 near Orlando. The flyover would take Osceola Parkway traffic over Victory Way.
•An extension of Western Way to Avalon Road, or County Road 545. Currently Western Way ends around the Flamingo Crossings development under construction.
•A Center Drive bypass to the west that will allow traffic heading south off Reams Road more direct access to Floridian Way.
Reedy Creek is also making steady progress on improvements to the road network near Downtown Disney. A ramp from eastbound Buena Vista Drive rising above the road and funneling drivers into the third story of a new parking garage should open Sept. 8. A half-mile spur extending off the westbound ramp leading from I-4 onto Epcot Center Drive should open in early October.
The road projects include:
A flyover will take resort traffic over the Magic Kingdom's toll plaza, providing easier access to travelers heading to hotels such as the Contemporary and Polynesian Village resorts, said John Classe, a Reedy Creek deputy administrator. Right now hotel visitors must drive through the parking plaza, even though they don't have to pay.
•A reconfiguration of Osceola Parkway at Victory Way, southeast of Disney's Hollywood Studios and north of ESPN Wide World of Sports Complex. A traditional intersection will be replaced with a flyover design similar to that at state roads 50 and 436 near Orlando. The flyover would take Osceola Parkway traffic over Victory Way.
•An extension of Western Way to Avalon Road, or County Road 545. Currently Western Way ends around the Flamingo Crossings development under construction.
•A Center Drive bypass to the west that will allow traffic heading south off Reams Road more direct access to Floridian Way.
Reedy Creek is also making steady progress on improvements to the road network near Downtown Disney. A ramp from eastbound Buena Vista Drive rising above the road and funneling drivers into the third story of a new parking garage should open Sept. 8. A half-mile spur extending off the westbound ramp leading from I-4 onto Epcot Center Drive should open in early October.