CastAStone
5th gate? Just build a new resort Bob.
Anyone else think it’s odd we haven’t seen any permits for DLH DVC yet?
Anyone else think it’s odd we haven’t seen any permits for DLH DVC yet?
| BLD2020-05279 | Disney - Confidential ; see correspondence for scope of work |
| BLD2020-05279 | DCA - BLDG 751 - Tenant Improvement: Install (1) rooftop truss structure. (Nov. 2020 - Jan. 2021)" |
| SGN2020-00122 | Disney - Confidential ; see correspondence for scope |
SGN2020-00122 | DCA - Redwood Creek Challenge Trail - Install (1) sign attached to existing marquee structure that reads "Santa's Holiday Visit!" (11-01-20 through 01-03-21) |
Wonder if the attached sign says: "Cancelled."Previous 'Confidential' permits were updated:
BLD2020-05279 Disney - Confidential ; see correspondence for scope of work
Now:
BLD2020-05279 DCA - BLDG 751 - Tenant Improvement: Install (1) rooftop truss structure. (Nov. 2020 - Jan. 2021)"
SGN2020-00122 Disney - Confidential ; see correspondence for scope
Now:
SGN2020-00122DCA - Redwood Creek Challenge Trail - Install (1) sign attached to existing marquee structure that reads "Santa's Holiday Visit!" (11-01-20 through 01-03-21)
| SGN2020-00153 | Disneyland Resort - See correspondence for scope 1515 S DISNEYLAND DR BLDG DD |
| BLD2020-05522 | DLH - See Correspondence. |
| BLD2020-05523 | DLH - See Correspondence |
| BLD2020-05585 | DLH - Central Energy Plant/ Boiler Room - Tenant Improvement: 7,592 sq.ft infill walls, stairs, new doors, pad for new equipment located on basement level and new stairs with vestibule, partial exterior demo located ground level. |
Looks like the DVC project.
BLD2020-05522 DLH - See Correspondence. BLD2020-05523 DLH - See Correspondence BLD2020-05585 DLH - Central Energy Plant/ Boiler Room - Tenant Improvement: 7,592 sq.ft infill walls, stairs, new doors, pad for new equipment located on basement level and new stairs with vestibule, partial exterior demo located ground level.
The permit requester works in imagineering. So I think you’re right.Looks like the DVC project.
BLD2020-04801 DTD - Buidling DD - Tenant Improvement: 3,871 sq ft to include new full-height wall to separate retail space from existing unoccupied space. Remove and replace existing roof mounted mechanical unit and re-route ducting. With electrical.
Makes sense since the Avenger land is supposed to open this year and would want a more prominent store location. I look forward to seeing if the dirty blankets get moved over to Rainforest Cafe then.Twitter rumor I read said that word is that a galaxys edge outpost store is to go there and the current store in dtd will be avengers themed
From Mouseplanet:
“
... We missed this building permit, but Disney in November filed to build a new wall to partition off the retail store from the restaurant space inside the vacant former Rainforest Cafe in Downtown Disney. The restaurant had a large gift shop at the entrance, and Disney seems to be looking for a way to open just that section.”
Should have known that @SSG didn’t miss it![]()
Updated : DTD - BLDG DD - Install (1) illuminated marquee sign and (8) non-illuminated decorative attachmentsUnknown signage permit, but Building DD is the old Rainforest Café.
SGN2020-00153 Disneyland Resort - See correspondence for scope 1515 S DISNEYLAND DR BLDG DD
| BLD2021-00105 | Disney - Confidential project ; see correspondence for scope 1515 S HARBOR BLVD 752 |
BLD2021-00249 | Mechanical to support DTD - Buidling DD - Tenant Improvement: 3,871 sq ft to include new full-height wall to separate retail space from existing unoccupied space. Remove and replace existing roof mounted mechanical unit and re-route ducting. With electrical. |
This was revised:First permit of the new year; yay!
It doesn't say anything; boo!
However, building 752 is the new merch store in Marvel Land and the reported stunt action happens on its roof.
BLD2021-00105 Disney - Confidential project ; see correspondence for scope 1515 S HARBOR BLVD 752
That's too lively for Star Wars, and also not immersive enough. Instead the employees will tell you all about their planet. Is the outpost a new planet? Different from Batuu?At least they're not replacing the crude robotic animals and storm effects.
| BLD2021-00302 | Electrical to support DTD - Buidling DD - Tenant Improvement: 3,871 sq ft to include new full-height wall to separate retail space from existing unoccupied space. Remove and replace existing roof mounted mechanical unit and re-route ducting. With electrical. |
| BLD2021-00341 | Electrical for a meter pedestal change out, same location. 1742 S DISNEYLAND DR WPS-21 |
NOooo!! I remember that pedestal!! Disney is destroying my childhood!!!!Some people have asked if I post every permit coming out of the resort. I do not because some of them are completely uninteresting. For example, this permit today appears to be for swapping out a utility meter by the DTD parking lot.
BLD2021-00341 Electrical for a meter pedestal change out, same location. 1742 S DISNEYLAND DR WPS-21
Apologies to any Water-Power-Sewer fans.
Register on WDWMAGIC. This sidebar will go away, and you'll see fewer ads.