ToT has had all of its scaffolding pulled down and there has been regular ride testing of the middle shaft. (just wait and look and you might see the doors open...about every 15 min.)
Just this week the construction wall has been pushed back to the front of Hyperion building while its on Rehab.
They pulled out a part of the concreet and are relaying the street and the curbs up to the tower. They should have the street poured by this weekend.
They have been working furiously to get the Fastpass area stuckoed. And the framing of the changing TOT/TLzone sign has been built. Inside the main lobby has some great detail and will be right at home with Floridas. Even an stain glass window/front door.
Dont plan on coming out to ride it any time soon...Ive heard late April early May for the opening.
Just this week the construction wall has been pushed back to the front of Hyperion building while its on Rehab.
They pulled out a part of the concreet and are relaying the street and the curbs up to the tower. They should have the street poured by this weekend.
They have been working furiously to get the Fastpass area stuckoed. And the framing of the changing TOT/TLzone sign has been built. Inside the main lobby has some great detail and will be right at home with Floridas. Even an stain glass window/front door.
Dont plan on coming out to ride it any time soon...Ive heard late April early May for the opening.