PERMITS

SSG

Well-Known Member
Original Poster
These refer back to 2020 permits for trailers used as temporary offices: (Plan Check Only) Disneyland Resort - Accessory Building: 2,240 sq ft for (3) new office trailers to be anchored.

BLD2021-00410Disney Resort - BOH - Modular #20055 - New Commercial Construction: 1,280 office modular building and utility connections. REF:BLD2020-05573
BLD2021-00417Disney Resort - BOH - Modular #20056 - New Commercial Construction: 320 sq.ft office modular building with electrical. REF:BLD2020-05573
BLD2021-00433Disney Resort - BOH - Modular #20057 - New Commercial Construction: 640 sq.ft office modular building and electrical. REF:BLD2020-05573
 

SSG

Well-Known Member
Original Poster
BLD2021-00801Disneyland - Jungle Cruise - Screen Wall: 12 ln ft x 12 ft high steel tube frame cladding and footings. 8 ln ft x 7 ft high fence. Add (2) additional feet to existing 28 ln ft retaining wall.
BLD2021-00804DLR - Maint BLDG 500 - Tenant Improvement: 2,500 sq ft to reconfigure existing 2nd floor Women's and Men's lockerrooms and restrooms. With mechanical, electrical and plumbing.
BLD2021-00805Disney - Confidential project ; see scope for correspondence
 

AJFireman

Well-Known Member
And added another confidential project at the Winery:

BLD2021-00554Disney - Confidential project ; see correspondence for scope 777 W KATELLA AVE 420 (Golden Vine Winery)


Updated Confidential Permit -

Description: DCA - Golden Vine Winery - Food and Wine Festival - Temporary Structures: Install (12) food kiosks, (3) refrigerators and (7) shade trellis'. (Mar 4 - Jun 1 2021)
 

Old Mouseketeer

Well-Known Member
BLD2021-00804DLR - Maint BLDG 500 - Tenant Improvement: 2,500 sq ft to reconfigure existing 2nd floor Women's and Men's lockerrooms and restrooms. With mechanical, electrical and plumbing.

Very interesting! Building 500 (that number is actually a legacy name--it's not the actual street address) used to be the ride vehicle maintenance building. It's actually made up of around four seperate industrial buildings that are connected (you can see them fill in from old aerial photos). It's now one half of the replacement for the Entertainment Building that was bulldozed for MMRR. I know someone who works in the (rather awkward) offices on the second floor and they described these leftover locker room/restrooms that were for the facilities workers who were moved offsite for MMRR.
 

SSG

Well-Known Member
Original Poster
BLD2021-01086DTD - BLDG G - Tenant Improvement: Construct new demising wall to separate units 103 and 104. Create new opening for door at rear of unit 104. Interior demolition to bring units to core and shell. With mechanical and electrical.
BLD2021-00978Disney - Gate 27 - Electrical for (1) 400 amp temporary power pole, (8) 100 amp subpanels, a 112kva transformer and (3) L650R receptacles.
 
Here is something to ponder. This may or may not have any relevance or it could be major. I live and I am at the end of a costly and lengthily prosses of obtaining building permits to build a single family home in San Diego county (three years and $80K not even gets you a shovel of dirt moved yet!). Due to covid and recent changes in regulations it has become almost impossible to get this done. The rumors here in San Diego is if you are even thinking of doing anything in the next decade get the permits NOW! And friends in the building department say that is exactly what people are doing.

How does my experience differ dramatically from Disney, I am not the counties largest employer and tax payer. I do not have a multi billion dollar developer managing my project. This is the first and last project I will ever build in California!

All this said they may still be pushing plans through that may or may never get done. I am sure just like us watching the building plans so is every other amusement/theme park. I wouldn't pass up the idea of them throwing fake ideas out there. Its cheap to submit plans, its expensive to get them approved!
 

SSG

Well-Known Member
Original Poster
Building 752 is the new AC merch store, and where Spidey will do his swinging routine.

BLD2021-01728 1515 S HARBOR BLVD 752Disney - Confidential Scope: see correspondence

BLD2021-01758Disneyland - BOH/Site Work - Electrical to remove and replace aluminum and copper conductors.

BLD2021-01716Electrical for 200 amp temporary power pole for DLH - Central Energy Plant/ Boiler Room.
BLD2021-01718Electrical for 200 amp temporary power pole for DLH - Central Energy Plant/ Boiler Room.
BLD2021-01719Electrical for 200 amp temporary power pole for DLH - Central Energy Plant/ Boiler Room.
 
Last edited:

CastAStone

5th gate? Just build a new resort Bob.
Premium Member
BLVD 752 is new AC merch store, and where Spidey will do his swinging routine.

BLD2021-01728 1515 S HARBOR BLVD 752Disney - Confidential Scope: see correspondence

BLD2021-01758Disneyland - BOH/Site Work - Electrical to remove and replace aluminum and copper conductors.

BLD2021-01716Electrical for 200 amp temporary power pole for DLH - Central Energy Plant/ Boiler Room.
BLD2021-01718Electrical for 200 amp temporary power pole for DLH - Central Energy Plant/ Boiler Room.
BLD2021-01719Electrical for 200 amp temporary power pole for DLH - Central Energy Plant/ Boiler Room.
Temporary power pole - potentially for DVC construction?
 