I am going to use this thread to track the major permits for the DHS Redevelopment.

South Florida Water Management district permits

10/26/2015 – SFMWD - 151026-6 (L402 Basin)

Description: Construction of 38.01 acre storm water pond west of World Drive, parking expansion, entrance ramp from Osceola Parkway, construction access road from World Drive to Cypress Dr.

Dates or Work: January 2016 and be complete in October 2018

Documents:

Application: http://my.sfwmd.gov/entsb/docdownload?object_id=0900eeea88b1fb88
Engineering Report: http://my.sfwmd.gov/entsb/docdownload?object_id=0900eeea88b1fbec
Plans: http://my.sfwmd.gov/entsb/docdownload?object_id=0900eeea88b1fc05
11/25/2015 – SFWMD - 151125-14 (H 1 Site Development)

Description: New fireworks launch area west of World Drive including fenced gravel yard, 3 large concrete slabs, 7 small concrete pads, block house building, storage building and access road.

Documents:

Application: http://my.sfwmd.gov/entsb/docdownload?object_id=0900eeea88be09dc
Plans: http://my.sfwmd.gov/entsb/docdownload?object_id=0900eeea88be0991
Engineering Report:
http://my.sfwmd.gov/entsb/docdownload?object_id=0900eeea88be09aa
 
Last edited:

danlb_2000

Premium Member
Original Poster
Orange County Permits 2016


1/6/2016 450 Cypress Dr, Catastrophe Canyon - DHS Back of House Package TF1.08 - Hubbard Construction Company
1/12/2016 511, 521, 541, 551 Cypress Dr - Back of House Package D1.01 - Hubbard Construction Company
1/12/2016 561, 595, 601, 611, 641, 643, 645, 649 Cypress Dr - DHS Back of House Package D1.02 - Hubbard Construction Company
1/12/2016 Muppet "B" Complex - General Construction - Barton Malow Company
1/13/2016 Muppet "B" Complex - General Construction - Barton Malow Company
2/10/2016 621 Cypress Dr - DHS Back of House Package D1.04 - Hubbard Construction Company
2/23/2016 375 Cypress Dr (AFI) - DHS Back of House Package Cosntruction Fencing Package 2 - Hubbard Construction Company
3/23/2016 396 Cypress Dr - DHS Back of House Demolition Package 1.10 - Hubbard Construction Company
3/24/2016 450 Cypress Dr (Cat Canyon area) - DHS Back of House Demolition Package 1.09 - Hubbard Construction Company
5/3/2016 555 Cypress Dr - DHS Back of House Package D1.03 North Wellhead Removal - Hubbard Construction Company
5/3/2016 540 Stage Lane - DHS Back of House Package D1.06 Area Development - Hubbard Construction Company
5/3/2016 371 Cypress Dr and 373 Cypress Dr - DHS Back of House Demolition Package 1.13 - Hubbard Construction Company
5/3/2016 540 Stage Lane - DHS Back of House Package D1.06 Demolition - Hubbard Construction Company
5/12/2016 585 Stage Lane - DHS Back of House Package D1.18 - Tour bridge #2 Area Development - Hubbard Construction Company
5/12/2016 Dhs Back Of House Guard Booth Area Development - 251 S Studio Dr - Hubbard Construction Company
5/16/2016 465 Cypress Dr - DHS Back of House Pargo Build Back Area Development - Hubbard Construction Company
6/8/2016 800 Ascot Dr - DHS BOH - Site Prep Package - Whiting Turner Contracting Company
6/16/2016 365 Cypress Dr - DHS Back of House Seconday Electric Power - Hubbard Construction Company
6/16/2016 500 Cypress Dr - DHS Back of House Area Development - Hubbard Construction Company
6/16/2016 500 Cypress Dr - DHS Back of House Area Development - Plumbing - Hubbard Construction Company
6/21/2016 400 Cypress Dr - DHS Back of House Area Development Utility Reroute - Hubbard Construction Company
6/21/2016 400 Cypress Dr - DHS Back of House Area Development Utility Reroute - Plumbing - Hubbard Construction Company
6/21/2016 400 Ascot Dr - DHS BOH - Foundation Work - Whiting Turner Contracting Company
6/21/2016 200 Ascot Dr - DHS BOH - Foundation Work - Whiting Turner Contracting Company
6/21/2016 400 Ascot Dr - DHS BOH - Foundation Work - Whiting Turner Contracting Company
7/14/2016 501 Cypress Dr - DHS Back of House - Well 2A Area Development - Hubbard Construction Company
8/10/2016 375 Cypress Dr - Project D - Sitework and Site Utilities Installation - Whiting Turner Contracting Company
8/17/2016 351 South Studio Dr - DHS BOH South Toll Plaza Fence - Hubbard Construction Company
8/19/2016 365 Cypress Dr - DHS Back of House Muppets Theater - Plumbing - Hubbard Construction Company
8/22/2016 520 Stage Land - DHS BOH PAckage D1.16 - Site Demo Package 2 - Hubbard Construction Company
9/6/2016 755 Stage Lane #B - DHS Back of House Package D1.06 Demo - Hubbard Construction Company
9/20/2016 375 Cypress Dr - Project D Site Utilities- Plumbing - Hubbard Construction Company
9/22/2016 384 Cypress Dr - Project D - 1004 - Package 1 - Foundations - Whiting Turner Contracting Company
9/26/2016 745 Stage Lane - DHS BOH Package D1.06 - Hubbard Construction Company
10/12/2016 251 S Studio Dr, H.S. - DHS BOH - Electrical - Hubbard Construction Company
10/13/2016 365 Cypress Dr (Muppets 3D) - DHS BOH - Exterior Demo and Modificaitons Package - Construction Llc
10/13/2016 555 Stage Lane #E (Buzz/Woody M&G) - DHS BOH - Exterior Demo and Modifications Package - Construction Llc
11/8/2016 400 Ascot Dr - DHS BOH Project A-400 - Trench Package - Whiting Turner Contracting Company
11/8/2016 151 Ascot Dr - DHS BOH Project A-151 F&B/Restroom Facility - Whiting Turner Contracting Company
11/15/2016 500 S. Victory Way - BOH Upgrades - Laydown Yard Fence - Hubbard Construction Company
11/28/2016 450 Cypress Dr - Project D - Bldg 1008 - Site Prep, Foundations and Structure - Whiting Turner Contracting Company
12/9/2016 465 Cypress Dr - BOH Upgrades - Pargo Building Area Development & Plumbing - Hubbard Construction Company
12/16/2016 200 Ascot Dr - DHS BOH Project A-200 - Ride Installation - Adena Corporation
12/16/2016 400 Ascot Dr - DHS BOH Project A-400 - Ride Installation - Adena Corporation
12/16/2016 800 Ascot Dr - DHS BOH Project A-800-02 - Area Development - Whiting Turner Contracting Company
12/16/2016 800 Ascot Dr - DHS BOH Project A-800-02 - Area Development - Whiting Turner Contracting Company
12/16/2016 585 Ascot Dr - DHS BOH Project A-585 - Building Modifications & New Addition - Whiting Turner Contracting Company
12/16/2016 480 Ascot Dr - DHS BOH Project A-480 Maintenance Building - Whiting Turner Contracting Company
12/16/2016 400 Ascot Dr - DHS BOH Project A-400-04 - Completion Package - Whiting Turner Contracting Company
12/22/2016 150 Cypress Dr - BOH Upgrade - Temporary Cast Walkway Reroute - Hubbard Construction Company
 
Last edited:

danlb_2000

Premium Member
Original Poster
2017 Permits


1/6/2017 500 S. Victory Way - Project D - Off-Site Laydown Single Wide Trailer and Turnstile - Whiting Turner Contracting Company
1/9/2017 251 S. Studio Dr - BOH Upgrades - Construction Zone Fence - Hubbard Construction Company
1/24/2017 400 Ascot Dr - DHS BOH Project A-400 - Foundations for Tower Cranes - Whiting Turner Contracting Company
1/24/2017 Studio Entrance - Surcharge Area - Overall site improvements and construction for project known as Osceola Parkway and Victory Way Early Works - Infrastructure Industrial Constructors Southeast Inc
2/2/2017 365 Cypress Dr - BOH Upgrades - Retaining Wall Construction - Hubbard Construction Company
2/2/2017 150 Cypress Dr - BOH Upgrades - Temporary Walkway Relocation - Hubbard Construction Company
2/14/2017 400, 800 Ascot Dr - Show Set Package 2 - Samson Metal Machine Inc
2/20/2017 400 Ascot Dr - DHS BOH Project A-400 - Install Package 1 Showset Pieces - Themeworks Inc
2/23/2017 384 Cypress Dr (Star Wars Land) - Project D - 1004 - Core & Shell Package - Ipd Agmt Parties
3/1/2017 228 Cypress Dr - New Operations Costuming facility - Construction of BOH costuming facility - Construction Llc
3/6/2017 Project D - Offsit Laydown Fence Installation (SWL) - 500 South Victory Way, #A - Whiting Turner Contracting Company, Cuningham Morris, Walter P Moore And Associates Inc, ...
3/6/2017 390 Cypress dr (SWL) - Project D - 1003 - Package 1 - Foundations - Whiting Turner Contracting Company, Cuningham Morris, Walter P Moore And Associates Inc, ...
3/6/2017 375 Cypress Dr (SWL) - Project D - 1000W - Amendment #3 - AD, Grading & Structure Revisions - Whiting Turner Contracting Company, Cuningham Morris, Walter P Moore And Associates Inc, ...
3/7/2017 950 N Studio Dr - BOH Upgrades - Swale Fence - Hubbard Construction Company
4/6/2017 648 Ascot Dr - DHS BOH Project A-648 - Interior Renovations - Whiting Turner Contracting Co, Helman Hurley Chavat Peacock Architects Inc, Contech Construction Llc, ...
4/17/2017 500 Ascot Dr - DHS BOH Project A-500 - Showset Package 5 - Icarus Exhibits Inc
4/26/2017 950 N Studio Dr - BOH Upgrades - Bus Loop Fence - Hubbard Construction Company
4/26/2017 390 Cypress Dr - Project D - 1003 - Package 2 - Structual Steel - Whiting Turner Contracting Company
5/12/2017 400 Ascot Dr - DHS BOH Project A-400 Props Package - Samson Metal Machine Inc
5/16/2017 480 Ascot Dr - DHS BOH Project A-480 - Low Voltage Installation and Terminations - Pro Sound And Video
5/16/2017 400 Ascot Dr - DHS BOH Project A-400 - Low Voltage Installation and Terminations - Pro Sound And Video
5/16/2017 585 Stage Lane - DHS BOH Project A-585 - Low Voltage Installation and Terminations - Pro Sound And Video
5/16/2017 800 Ascot Dr - DHS BOH Project A-800 - Low Voltage Installation and Terminations - Pro Sound And Video
5/16/2017 151 Ascot Dr - DHS BOH Project A-151 - Low Voltage Installation and Terminations - Pro Sound And Video
5/16/2017 648 Stage Lane - DHS BOH Project A-648 - Low Voltage Installation and Terminations - Pro Sound And Video
5/16/2017 200 Ascot Dr - DHS BOH Project A-200 - Low Voltage Installation and Terminations - Pro Sound And Video
5/18/2017 386 Cypress Dr - Project D - 1001 - Package 1 - Foundation & Structural Steel - Whiting Turner Contracting Company
5/23/2017 4000 Ascot Dr - BOH Project A-400 - Showset Package 8 - Facility 505 - Garage Graphics Visuals Inc, Elemoose
 
Last edited:

danlb_2000

Premium Member
Original Poster
So new retaining pond, for the displaced water from the expansions/ new parking structures?

Yes. The areas shown on this map in yellow are current un-paved areas that will become parking or other structures.

Capture.JPG
 

danlb_2000

Premium Member
Original Poster
Cross posting this here since the original thread about the permit is still in the main forum...

Disney has filed with the South Florida Water Management District for a modification to this permit. The changes include small reconfigurations of the Osceola Parkway ramp and the access road. The modification also adds a temporary conveyor belt that will be used to carry dirt from the excavation of the new retention pond over to the park where it will be used for fill. I guess they decided that this would be more efficient then trying to move it with trucks.

The modification to the Osceola ramp is interesting because it shows what appears to be the start of an extension all the way to World Drive. Maybe this will become the new Osceola to World Drive ramp when all the work is done.

capture-jpg.134186
 

cjkeating

Well-Known Member
Cross posting this here since the original thread about the permit is still in the main forum...

Disney has filed with the South Florida Water Management District for a modification to this permit. The changes include small reconfigurations of the Osceola Parkway ramp and the access road. The modification also adds a temporary conveyor belt that will be used to carry dirt from the excavation of the new retention pond over to the park where it will be used for fill. I guess they decided that this would be more efficient then trying to move it with trucks.

The modification to the Osceola ramp is interesting because it shows what appears to be the start of an extension all the way to World Drive. Maybe this will become the new Osceola to World Drive ramp when all the work is done.

capture-jpg.134186

Great info. Really interesting that they are building a conveyor. It seems a little bit overkill on paper but if it makes things go quicker then I am all for it! Was the original permit approved or have they submitted this as a modification pre-approval?
 

cjkeating

Well-Known Member
Great info. Really interesting that they are building a conveyor. It seems a little bit overkill on paper but if it makes things go quicker then I am all for it! Was the original permit approved or have they submitted this as a modification pre-approval?

I just had a look at the original permits, the new pond is going to be huge and displace a lot of soil/dirt. I wonder if they have plans for what is displaced for something other than filling in the current pond hence the conveyor.
 

danlb_2000

Premium Member
Original Poster
Great info. Really interesting that they are building a conveyor. It seems a little bit overkill on paper but if it makes things go quicker then I am all for it! Was the original permit approved or have they submitted this as a modification pre-approval?

The original was approved.

The conveyor makes a lot of sense because the only way they could get trucks to where the fill has to go would be through the existing entrance road which would be very disruptive to guest traffic.
 